Interior Door hardware/ selection/ data sheet/ prepared

INTERIORS · interiors.interior-door-hardware-selection-data-sheet-prepared
Not Started

Current — R11

Start
2026-04-24
Finish
2026-05-05
Duration
10 days
Resource
MCP
GC row
#132

Predecessors

None.

Timeline across revisions

Only 1 revision ingested so far. Once a new weekly PDF lands, this table will show how dates and duration drift over time.

RevExportedStartFinishDurStatus
R11 2026-04-17 2026-04-24 2026-05-05 10d Not Started